Tenders for Olympic Hockey Stadium planned in August

At the start of a new fiscal year, many Japanese government organisations make pre-announcement regarding large public works tenders they plan to do in the coming year.

Tokyo Metropolitan Government announced this week that it is planning a number of tenders related to the preparations for the 2020 Olympic Hockey Stadium. TMG has split up construction of the stadium into a number of separate tenders, a practice common in Japan.  Presently, it is not known whether the tenders will be conducted under international WTO regulations.

 

Name

Expected date

Procedure

New Construction of Ooi Hockey Stadium

End of August

Open tender

Electrical installation work for Ooi Hockey Stadium

End of August

Open tender

Ventilation and air-conditioning work for Ooi Hockey Stadium

End of November

Designated tender after application

Plumbing, water supply infrastructure for Ooi Hockey Stadium

End of November

Open tender

Elevator installations at Ooi Hockey Stadium

End of November

Designated tender after application

 

Construction work for the stadium needs to be completed by June 2019. Proceedings regarding the tender are conducted by TMG’s Bureau of Finance, Public Building Construction and Maintenance Division.

 

Source: TMG